= calendar effort (in months) = total effort (in man-months) = Number of people working on the project = Degree of partitionability (where 0 = not partitionable, and 1 = totally partitionable) = base training/ramp-up time (months per person) = average intercommunication overhead between two people (in months/person*person) = base sub-task communication overhead (in months)